Are engines aviation's bottleneck? If so, when does it end?

At MRO Australasia in Brisbane last week, Qantas Domestic CEO Markus Svensson described engines as one of the biggest challenges facing the industry. It's a fascinating insight, and easy to nod along with a line like that and move on, but I wanted to know what's behind it: how big the problem really is, how long it lasts, and more importantly who feels it first.
An aircraft without engines is a glider
For much of 2025 and into early 2026, Airbus had finished A320-family jets parked because it couldn't get the engines to put in them. Air Data News counted around sixty of these "gliders" in the summer of 2025.
In February, Airbus CEO Guillaume Faury told CNBC it was "an unsatisfactory situation with less engines than we would need" for 2026. What was missing from Pratt & Whitney, he said, was very significant, and CFM couldn't deliver more than it had already committed.
By Airbus's half-year results in July, the picture had changed in one important way: it said it no longer had aircraft ready for handover and waiting solely for engines. That doesn't mean the constraint has gone. Airbus does not have a buffer of Pratt engines, and the volumes agreed with Pratt still shape its 2026 and 2027 ramp-up.
Airbus Commercial Aircraft CEO Lars Wagner told reporters in July he expects the "protracted" engine problems to be resolved by 2028, but that's just Airbus's view, not a guarantee from the engine makers.
Two engine makers, two different stories
Pratt & Whitney is still working through the powder metal issue that forced accelerated inspections of its geared turbofan fleet from 2023. Pratt's guidance was that GTF-related groundings would average about 350 aircraft a day through the end of 2026. Aircraft-on-ground levels fell about 25% in the first half of the year, and RTX told investors they were stable in the third quarter and expected to improve in the fourth and into 2027.
Output is rising, with overhaul output on the PW1100 up 35% in the third quarter, the GTF engine backlog is now over 8,000. The first aircraft powered by the upgraded GTF Advantage engine has been delivered to United, and Pratt expects that engine to double time on wing.
GE and CFM are in a different position. LEAP deliveries are up 26% so far this year, with five consecutive quarters of at least 500 engines. GE says LEAP-related groundings have fallen to nearly zero since the summer, and that LEAP shop turnaround times are about two weeks shorter than at the end of 2025.
So the supply of new engines is improving, unevenly, and faster for one manufacturer than the other.
New engines are only half the problem
Every engine delivered today is a future shop visit, and as we stand today, the shops are full.
On its latest earnings call, GE said more than 100% of its planned fourth-quarter internal shop visits were already in its facilities, with more engines waiting to be inducted, and that more than 95% of expected spare parts revenue for the quarter was already in backlog.
Spare parts delinquency rose from the previous quarter even though material availability is improving. Of one engine, the GE90, GE's CEO said it's "hard to get parts, hard to get an engine." Pratt has told investors its GTF aftermarket is sold out through 2027 and beyond.
Demand for shop visits is going up, not down. GE reports LEAP shop visits up about 40% in the quarter and expects about 25% growth in 2027. Retirements of older CFM56 engines have run below what GE expected, and about two-thirds of that fleet hasn't yet had a second shop visit. Aircraft that stay in service longer need more maintenance, not less.
IATA adds a structural point to consider. Engine and systems makers now earn a larger share of their profit from the aftermarket than from new equipment, and in many cases component repairs are only possible through the manufacturer or its licensees. IATA says that gives the OEMs limited interest in developing new repair solutions, which raises costs and lead times for airlines.
Who gets served first?
You'd reasonably expect a priority list but I couldn't find a published one. What the evidence shows is a set of pressures, not a rule:
Defence and business aviation compete with airlines for the same raw material. IATA says they compete directly for the same castings, forgings and engine capacity, and often accept higher prices and shorter terms, which leaves airlines squeezed. An executive from Air France Industries KLM Engineering and Maintenance warned at a recent conference that military demand could take priority over civil.
Pratt is splitting the same engines between the factory and the fleet. It is balancing deliveries to Airbus against engines for airlines that need spares, and Airbus itself described a "tug of war" with airlines over supply.
Size seems to help. An industry executive quoted by AviTrader said that in systemic shortages, larger operators are prioritised for in-demand parts, leaving smaller operators vulnerable.
None of this amounts to a published policy that says who is served first. But the pattern is consistent: the biggest customers, with the longest service agreements, have the most leverage when capacity is tight.
So how long?
Honestly, it depends on which part of the problem you mean.
New engine output is improving, with LEAP groundings having largely cleared, Pratt's are expected to ease into 2027, and Airbus is planning around 2028 for its supply to normalise.
Maintenance capacity however, is the slower fix. It depends on materials, parts and skilled labour, and the shop visit wave from engines delivered over the past several years is only now arriving. What this means for people who fly is delayed growth, higher leasing costs and longer disruptions, as IATA puts it. For people who work in maintenance, it means the engine shop is going to stay a constrained place for some time.
Nobody can say precisely when it eases, and the honest answer from the engine makers themselves is "improving", not "solved."
Jotore Aviation Consulting provides maintenance strategy, regulatory compliance, and CAMO/AMO advisory services to Australian aviation operators. For more aviation industry analysis, visit www.jotoreaviation.au
References
CNBC, Airbus 2026 delivery guidance and engine shortage (19 Feb 2026): https://www.cnbc.com/2026/02/19/airbus-earnings-fy-q4-boeing-deliveries-a320-airbus-2026-boeing-recovery.html
Airways, Airbus H1 2026 results and "gliders": https://www.airwaysmag.com/new-post/airbus-h1-2026-results-delivery-target
TravelRadar (reporting Reuters), Airbus on Pratt engines and 2028 (21 Jul 2026): https://travelradar.aero/airbus-says-its-pushing-for-more-pratt-whitney-engines-in-2027-as-shortages-continue-to-constrain-a320neo-output/
Simple Flying, Airbus delivery target and gliders: https://simpleflying.com/airbus-must-deliver-84-jets-month-hit-2026-target/
RTX Q3 2026 earnings call transcript: https://www.fool.com/earnings/call-transcripts/2026/10/20/rtx-rtx-q3-2026-earnings-call-transcript/
Investing.com, RTX at the Baird 2026 conference: https://www.investing.com/news/transcripts/rtx-at-baird-2026-global-industrial-conference-backlog-drives-outlook-93CH-5016208
Leeham News, RTX Q2 2026 results: https://leehamnews.com/2026/07/23/rtx-posts-strong-quarter-as-pws-geared-turbofan-saga-continues/
Aviation Week, Pratt GTF MRO outlook (350 aircraft guidance): https://aviationweek.com/mro/aircraft-propulsion/pratt-cautiously-optimistic-gtf-mro-outlook
GE Aerospace Q3 2026 earnings call (transcript): https://www.benzinga.com/news/26/10/62464248/ge-aerospace-q3-2026-earnings-call-transcript
AOL, GE Q3 2026 call summary: https://www.aol.com/articles/ge-ge-q3-2026-earnings-152842000.html
IATA, Aviation Supply Chain: https://www.iata.org/en/programs/ops-infra/techops/aviation-supply-chain/
Aviation Week, Europe's engine aftermarket: https://aviationweek.com/mro/aircraft-propulsion/geopolitics-material-shortages-reshape-europes-engine-aftermarket
AviTrader, component management and the supply chain: https://avitrader.com/2026/03/14/trends-in-component-management-and-the-supply-chain/
Aviation Week podcast, MRO Australasia 2024: https://aviationweek.com/podcasts/mro-podcast/podcast-what-we-learned-mro-australasia